Four checks before delivery
| Model | Electrical specification | Working space | What to confirm |
|---|---|---|---|
| Artica Element | 208 to 240 V, 60 Hz, single phase: MCA 26 A; separate supplier current label 40 A. 208 to 240 V, 50 Hz, single phase: MCA 32 A; separate supplier current label 50 A. | Working space: 105 x 71 x 95 in (W x D x H). | Confirm the frequency-specific manual and circuit design; the supplier current label is separate from MCA. |
| Artica Vortex | 208 to 240 V, 60 Hz: MCA 50.1 A single phase / 24.9 A three phase. | Chamber: 57 x 59 x 116 in (W x D x H). Control engine: 42 x 42 x 84 in (W x D x H). Outdoor unit: 68.5 x 41.8 x 68.9 in (L x D x H). | Request a drawing locating all three components and their service and delivery clearances. |
| Artica Ethos | 208 to 240 V, 60 Hz: MCA 88 A single phase / 43.1 A three phase. | Product page: 103 x 67 x 100 in (W x D x H). Comparison page: 103 x 95 x 116 in (W x D x H). | The two published envelopes differ. Obtain an agreed drawing for the offered revision before sizing the room. |
Working spaces describe separate components, not a combined room plan. Have the supplier and installer confirm the selected revision, full layout, ventilation and local requirements.
If you are still choosing the equipment format, start with the whole-body selection guide. Then budget site work separately from the published equipment price and complete these checks before booking delivery.
Read the four checks as a checklist
- Delivery: confirm packaged dimensions, route constraints, unloading, lifting and who performs the work.
- Installed space: separate equipment footprint from operating clearances, service access and any external modules.
- Utilities: match the offered power or nitrogen configuration, its current installation requirements and the site's reviewed provisions.
- Handover: agree on commissioning checks, document delivery, operator training and the parties responsible for open items.
1. Delivery path
Get the packed and unpacked dimensions, weight and required orientation. Measure exterior access, the loading area, doors, corridors, elevators, corners, ceiling height and the final approach. Ask who removes the packaging, who brings lifting equipment and what happens if the planned route is blocked on the day.
Match the delivery term to the actual handoff
For equipment crossing a border, put the agreed delivery term beside the destination and itemized freight scope. If the agreement uses an Incoterms rule, keep the exact rule, named place or point and edition with it. A street address alone does not tell the rigging crew which work has been bought.
| Delivery task | What to confirm before arranging the move |
|---|---|
| Delivery term and destination | Agreed wording, edition if applicable, precise place and matching order revision |
| Transport risk and insurance | The agreed handoff point, responsible parties and coverage for the actual transport stages |
| Import responsibilities | Importer of record, entry-document owner, customs advice and separately priced duties, taxes or fees |
| Physical placement | Who unloads, moves the package inside, rigs each module and signs the condition report |
| Damage, delay and acceptance | Applicable notice process, responsible contact, payment milestones and separate commissioning documents |
Baldev Bhinder's guest explanation on ICC Academy separates delivery and risk from ownership and payment. Have your purchase agreement define each event; paying freight alone does not assign unloading or placement.
For a US import, CBP's customs-broker FAQ explains that hiring a broker is not a general legal requirement, while the importer remains responsible for understanding requirements and compliant importation. Name the importer and obtain qualified advice on the entry, tariff code, duty and permission to import or operate the exact device.
Match the agreed scope to the landed-cost check, then distinguish receipt from commissioning in the handover checklist.
2. Room and working clearance
Use the working-space requirement for the configured installation, not just the machine footprint. Include door movement, operator position, emergency access, cleaning and service access. The Element sketch below shows the size difference; the room tool lets you check the published floor envelope and height separately.
Compare the published Element, Vortex and Ethos dimensions
The machine's footprint and the space it needs to operate are different numbers. Artica lists an Element footprint of 76 x 36 x 90 inches (approx. 193 x 91.4 x 228.6 cm) and a larger stated working envelope of 105 x 71 x 95 inches (approx. 266.7 x 180.3 x 241.3 cm). The Artica Vortex comes as a chamber plus separate control and outdoor units, and Ethos now shows conflicting working-space figures: its product page lists 103 x 67 x 100 inches (approx. 261.6 x 170.2 x 254 cm), while its comparison article lists 103 x 95 x 116 inches (approx. 261.6 x 241.3 x 294.6 cm). Both were checked October 11, 2026. Ask Artica for the drawing for your selected layout rather than choosing the smaller envelope.
Rounded conversions help you read the drawings. Use the original units, tolerances and complete layout when asking contractors to price the room.
Artica Element provides a concrete example. The supplier lists a 76 x 36 x 90 in main unit and a 105 x 71 x 95 in working space, width x depth x height. Numeric check: October 11, 2026.
Both rectangles use one scale, shown separately so this sketch does not assign the extra space to a particular side. It does not show door movement, a safe route, approved shared clearances or a required ventilation arrangement. Check the complete configured drawing and the clear height, not floor area alone.
Manufacturer dimension publication - Try the simple room sketch
3. Electrical service
From the current manual, get the voltage, phase, frequency, full-load current, breaker, disconnect, receptacle or hardwire detail, conductor and grounding requirements. Ask whether auxiliary equipment needs its own circuits.
Published requirements vary widely, even within one brand:
- Artica Element - 208-240 V, single phase; published 60 Hz specifications include 40 A and MCA 26 A, while 50 Hz specifications include 50 A and MCA 32 A. Confirm the selected package and original electrical terms
- Artica Vortex - 208-240 V, 60 Hz; published MCA 50.1 A single phase or 24.9 A three phase
- Artica Ethos - 208-240 V, 60 Hz, MCA 88 A single phase or MCA 43.1 A three phase
- CryoBuilt Everest - ambiguous published 230vp3h, 70amps string; exact voltage, phase and frequency remain unverified
- MECOTEC cryo:one+ - 460 V, three phase, 60 Hz, 32 A for the published US configuration
Never copy one model's circuit into another project. A qualified electrician should review the final supplier document against your building's actual service.
Check US product certification against the actual unit
Ask your project electrician and the responsible local authority which approvals apply to the proposed equipment and installation. OSHA's NRTL FAQ explains that recognition covers particular product-safety standards and recognized laboratory sites. Where OSHA requires NRTL approval, a CE mark does not replace it. The FAQ also describes limited alternatives; this checklist does not decide whether one applies to your project.
Check what the certification covers. UL Solutions explains Component Recognition as certification for parts or subassemblies used within an end product, under stated conditions of acceptability. That is different from certification of a complete standalone product. A component mark alone is not certification of the complete chamber.
For the installation review, collect:
- A photograph of the supplied unit's identification and certification markings, tied to its model and serial number.
- The certification body, certificate number or file identifier, covered model and electrical configuration, applicable standard and conditions.
- Whether the certification covers the complete assembly or only named parts, and how it matches the package being delivered.
- The qualified reviewer's decision, differences still to resolve and any required follow-up before installation or use.
Ask the issuer to confirm the certification number, model and configuration. A logo or certificate image alone is not enough, while a missing public download does not prove certification is absent. Confirm product certification, site acceptance and intended use separately.
4. Refrigeration and condenser planning
Ask whether the refrigeration is self-contained or split, where the heat goes and whether an outdoor unit is needed. For a split system, confirm distance and height limits, line routing, wall or roof penetrations, condensate, weather exposure, vibration, noise and access for future service.
The written quote should say who supplies, installs and warrants each part of the refrigeration connection.
5. Temperature and humidity
Ask for the permitted and preferred room temperature and humidity, running heat output and the building cooling capacity needed to hold those conditions. Confirm what alarms, shutdowns or loss of capacity occur outside the permitted range.
6. Nitrogen delivery, storage and room controls
For a nitrogen system, get the exact storage and connection plan: tank type, capacity, delivery access, fill schedule, piping or hose route, ventilation, oxygen monitoring, alarm placement, emergency procedure and local authority requirements. The final design has to come from the equipment documents, the gas supplier and qualified local professionals.
OSHA has documented a fatal oxygen-deficient atmosphere during liquid-nitrogen dispensing where adequate ventilation and oxygen monitoring were missing. The incident illustrates the hazard; the right controls depend on the actual equipment, room and jurisdiction.
7. Permits, landlord approval and insurance
Ask the local authority which building, electrical, mechanical, fire or business approvals apply. Get landlord approval for structural work, penetrations, outdoor equipment, gas storage and signage. Tell your insurer the exact equipment type and safety controls. Log every approval as pending, approved or rejected.
8. Network, software and privacy
If the chamber is remotely monitored, ask about network requirements, who owns the account, subscription cost, what data is collected, remote-access controls, the update policy and what support looks like when the connection drops. Confirm whether the software account transfers if you sell the equipment.
9. Commissioning and acceptance
Agree what "accepted" means before the equipment arrives.
- Correct model and configuration delivered
- Visible shipping damage documented
- Installation matches the approved plan
- Safety controls tested
- Alarms and shutdown behavior demonstrated
- Operating cycle completed
- Operator training completed
- Manuals, credentials and service contacts handed over
- Open defects and completion dates documented
- Warranty start date confirmed
Where the contract allows, tie the final payment to this documented acceptance.
Pre-site checklist
Fill this in for the exact model, or copy it into your project file.
Open your checklist notes
Resolve document differences before freezing the room plan
Keep three sets of dimensions: the equipment as delivered, the space it needs to operate, and the space needed to install and service it. Include every chamber, mechanical cabinet, condenser, tank and connection route, and note the document revision, units, reviewer and any differences to resolve.
If publications disagree, ask the supplier for the applicable drawing before finalizing the layout. The smaller number may not apply.
See five published layout conflicts and what would resolve them
| Layout question | What the maker says | What to ask |
|---|---|---|
| Component mistaken for complete equipment | Vortex control-engine dimensions are smaller than the chamber dimensions on the exact model page | Current component layout, packed dimensions and route survey |
| Non-equivalent floor units | CRYONiQ physical material pairs 20 square feet with 6 square meters; 20 square feet equals about 1.86 square meters, while 6 square meters equals about 64.6 square feet | Corrected supplier drawing with dimensions and clearance labels |
| Inconsistent weight conversion | CRYONiQ XC lists 370 kg and 700 lb; the metric value is about 815.7 lb | Confirmed equipment and packed masses, rigging plan and qualified floor review |
| Chamber and machinery treated as one footprint | e-Arctic publishes separate module, working and installation dimensions for chamber and machinery | Supplier-approved combined room and service layout |
| Page and product sheet disagree | Current CryoMe Pro publications show different heights | Current revision confirmation before measuring doors and ceiling |
These are questions to put to the supplier, not alternative installation requirements. Never pick the smaller dimension to make a room fit. See Vortex, CRYONiQ physical specifications, CRYONiQ XC, XC Plus, e-Arctic and CryoMe Pro. Vortex and e-Arctic dimensions and the CRYONiQ weight and floor-unit figures were checked October 11, 2026; CryoMe Pro was checked October 6.
For the separate e-Arctic chamber and machinery dimensions, continue to the CRYO Science layout and US-version checks. For a Pro proposal, use the Cryomed and CryoMe Pro configuration checks to keep the model generation and offered US package together.
Close the configuration matrix before contractor pricing
| Installation item | Ask the supplier | Ask the local reviewer |
|---|---|---|
| Offered version | Model, revision, region, cooling option and serial/build state if known | Exact equipment against the site plan |
| Electrical connection | Voltage, phase, frequency, original current label and circuit document | Available service, circuit design and applicable approval |
| Heat and water | Indoor/outdoor modules, heat rejection, any required water connections | Routing, cooling capacity, permissions and access |
| Working envelope | Every module, doors, service space, tank space and delivery dimensions | Actual room, delivery route and floor constraints |
| Scope handoffs | Named parties, included work and the point where each supplier scope ends | Priced excluded work, responsible contractor and completion documents; no missing or duplicated line |
| Document sequence | Current package, drawings, instructions and agreed revisions | Receipt, review and acceptance confirmed separately before the next task |
| Commissioning | Included tests, training and handover documents | Responsible party, acceptance date and outstanding items |
Use the itemized quote comparison to price the agreed boundaries. Keep a supplier-included item visible with its written scope instead of adding the same contractor amount again. Assign any unclear work in the dependency checklist and handover checklist.
The Antarctica Electric product page, checked October 6, 2026, shows why electrical and water-cooled variants must be identified before local work is priced. No general installation slogan replaces this matrix. It is a purchasing checklist, not an engineering design.
Operator and training readiness
Ask which theory and practical tasks each operator role must complete on the exact model and manual revision. A theory certificate or an attended call alone may leave practical preparation unfinished.
Schedule training against the actual delivery and commissioning plan. Confirm which named roles must attend, who provides the training and whether the required equipment, utilities and any applicable gas supply will be ready. Keep unfinished work on the handover checklist and confirm operator preparation separately from installation.
The CryoMe launch-package publication, checked October 14, distinguishes theory and practical preparation and limits its stated training-price inclusion to electric chambers. Ask for the nitrogen cryosauna training package separately. Have the offer name the preparation, format and costs, then obtain confirmation of the tasks completed on the quoted unit.
Plan operator training
From order to opening
Use the dependency plan before committing to the next stage. At delivery and commissioning, complete the handover checklist. Track payments, coverage dates and the opening date separately in the timeline.
Start with an installation responsibility matrix
The seller may deliver the chamber without arranging the building work. Before setting a delivery date, name the party responsible for each applicable task and who will accept its completion.
- Supplier: ordered configuration, current drawings, delivered scope and commissioning obligations.
- Buyer and landlord: permission for the work, access, room and external-equipment locations.
- Electrical and refrigeration / HVAC contractors: the work assigned to them under the configured design.
- Gas supplier and responsible site professionals: nitrogen supply and applicable site provisions where relevant.
- Local authorities: permits and inspections that apply to the location.
- Operator organization: staffing, training and completed handover documents.
Have each party accept its tasks in writing, even when one company fills several roles. An unassigned task remains a project gap.
Still choosing a site? Add your site questions to the buyer brief before asking for an itemized quote.
Download the installation responsibility checklist (CSV)
If the cooling technology is undecided, start with the six site constraints. This matrix assigns work; it does not specify circuits, ventilation rates or an operating procedure.
Track the installation dependencies
Track who must finish each task and which later work depends on it.
- Supplier configuration confirmed.
- Delivery route accepted.
- Site drawings accepted by the relevant parties.
- Applicable inspections completed.
- Commissioning and training completion confirmed.
Give each task an owner, due date, supporting document and revision, status and open question. Confirm completion separately from receiving a document, and leave missing information blank.
Download the installation dependency worksheet (CSV)
For each task, note whether its document is unknown, requested, received, accepted or not applicable with a reason. A document you have received still needs review. Make payments and book delivery only after the documents they depend on are accepted and the work is done.
Build and download your installation dependency register
Add the owner, due date, document and open question for each task. Download your notes before leaving; blank answers stay unknown. Confirm installation and operating readiness with the supplier and responsible local professionals.
Download and copy need JavaScript. Use the table and form below for your own notes.
- Choose the configuration
- Assign site responsibilities
- Close dependent tasks
A complete equipment handoff
At handover, collect the seller and equipment identity, approved site drawing, operating manual, commissioning results, training confirmation, current warranty, service contacts and open-defect list. Name the model, serial number and revision, and assign an owner and due date to missing documents. Installation acceptance and permission to operate need their own confirmations; a product sheet provides neither.
Keep one handover file for the package, with separate arrival and commissioning entries for each module. Attach the packing list, condition report and drawings. Have the responsible parties sign off completed work and assign any open items before the next contractual decision.
Check delivery and handover
Keep purchase and opening events separate
Plan opening after the supplier's delivery lead time: site work, commissioning and operator preparation still need completion. Have the agreement name the milestones that release payments, start coverage or change cancellation terms.
| Event | Document to request | What must be ready |
|---|---|---|
| Configuration and order accepted | Named model, options, revision and agreed package | Destination documents and exclusions resolved |
| Production begins | Contract definition and dated supplier confirmation | Deposit/cancellation boundary and configuration-change terms |
| Equipment dispatched | Shipment and delivery documents | Carrier, route, unloading and storage arranged |
| Equipment received | Receipt and agreed condition check | Damage or missing items documented under the agreement |
| Installation and commissioning accepted | Named tests, completed work and open-defect list | Site work, utilities and applicable gas arrangement ready |
| Operators prepared | Confirmation of theory and practical preparation for named roles | Trainer, exact equipment, instructions and supplies available |
| Service coverage begins | Current contract and stated start event | Responsible provider, contact window and coverage confirmed |
| Business opens | Your readiness decision and required local approvals | Open site, operator and commercial conditions resolved |
Keep the original and revised promises, time zones, responsible parties and completion documents in the dependency register. Confirm commissioning separately from shipment, and training separately from installation. Transfer actual deposits, balances and finance payments to the cash schedule without counting the equipment principal twice.
Check operator readiness for training and the support file for service contacts and remaining faults. Keep both with the current manual and installation decisions.
Sources
- Vortex product page - Artica SystemsArtica Systems
- CRYO Science e-Arctic Performance product page: components and US versionCRYO Science
- Provider's Guide to Whole Body Cryotherapy, version 1.1 (PDF)Global Wellness Institute
- OSHA inspection 1448201.015: liquid-nitrogen fatalityU.S. Occupational Safety and Health Administration
- CRYO XC / XC Plus brochure (PDF)CRYONiQ
- CRYO XC physical specificationsCRYONiQ
- CryoMe Pro specifications: overall height and product-sheet linkCryomed / CryoMe
- CryoMe business packageCryomed / CryoMe
- Antarctica Electric FAQ: head-out use and electrical optionsVacuactivus
- CRYO XC US product page: XC vs. XC Plus comparisonCRYONiQ
- CRYO XC Plus US product page: feature comparisonCRYONiQ
- OSHA's Nationally Recognized Testing Laboratory Program: FAQUS Department of Labor / OSHA
- The UL Component Recognition ClassificationUL Solutions / The Code Authority
- Incoterms 2020: CFR vs FOB & the title transfer myth (ICC Academy guest article)Baldev Bhinder / ICC Academy guest contributor
- Do I need a customs broker to clear my goods through CBP?US Customs and Border Protection